CONSTRUCT
mountain peak case study icon

Mountain Peak

Delivering reliable, cost-predictable power when traditional construction models fell short

Case Study

Problem

The electric power cooperative customer left their long-term power supplier and sought a resource located on their distribution system.  The customer was looking for speed to market, with great intention to modernize its portfolio while providing cost predictability for its members. Many traditional Engineering, Procurement and Construction (EPC) providers declined to bid on the project due to the size and scope – therefore Kindle pursued an alternative solution.

Solution

Mountain Peak Power was developed by Kindle to address the specific needs of the electric cooperative. With a signed, long-term contract with the customer in place, Mountain Peak took an atypical approach to EPC.  Kindle utilized its existing EPC organization to manage all elements of constructing and commissioning the project. It took less than two years for Mountain Peak Power to go from project conception to project commercialization.

01

Kindle challenged its Engineering and Construction teams to put together a plan to:

Manage the construction of the Mountain Peak Power plant via a small number of vendor contracts and utilizing Kindle’s existing EPC Organization

Maintain the original economics of the project

Achieve COD in line with the long-term customer contract

02

The Kindle team then identified multiple Tier 2 contractors who could provide the services of an EPC provider, but under an EPC Management model overseen by Kindle (General Contractor Model), and negotiated contracts with the General Contractor.

03

The Engineering and Construction team then:

Developed a schedule to demonstrate how all the vendors and equipment will be available to achieve completion by June 01, 2025

Convinced equity sponsors to commit capital to move forward with financing and construction based on Kindle’s General Contractor plan

Purchased key equipment

Provided written materials, held calls with Lenders to describe Kindle’s General Contractor plans and how risk will be mitigated during construction

Location:Keenesburg, CO
Partner:United Power
Customer Type:Public Power; Cooperative
Completion Date:September 2025
Facility:Simple Cycle Peaking
Project Size:162 MW
Our Process - Construct

Impact

162 MW

Power Supply

Mountain Peak

Mountain Peak Power commenced construction in August of 2024 utilizing the General Contractor Approach. Successfully constructing Mountain Peak Power under a General Contractor model demonstrated Kindle's ability to continue developing and building projects independently or with an EPC contract.

Outcomes:

Provided Kindle a process step in transitioning construction solutions from EPC to EPCM alternative models

Enables Kindle to continue to be a solution provider to entities pursuing new power supply during a time where there are limited alternatives for how to construct new plants

More Case Studies

Initiate Your Project

Whether you need new power generation, want to optimize existing assets, or need to structure power investments, we'll work with you every step of the way and create a customized solution that delivers results.

Contact Us